Description and objectives

The goal is to pool the results of the different previous workpackages to build the overall device resulting from this project, to test the device and to prepare, perform and analyze the tests on at least one industrial situation. The provision of test equipment by the end user is required for the performance of the tests and for the performance of the final device.

Start date

01/09/2019

Duration

18 months

Task leader

Sector

Sub-tasks and delivrables

T.6.1. Conception of the global device

D.6.1. Specifications of the emulator

T.6.2. Definition of the prototype test

D.6.2.a. Emulator
D.6.2.b. Definition note of the device

T.6.3. Prototype test and update

D.6.3. Definition note

T.6.4. Identify and characterize interfaces

D.6.4. Results of prototype test

T.6.5. Device test for the end-user

D.6.5. Monitoring data obtained from sensors
D.6.5. Test result in real conditions and defintion of the final 
device

Milestone

Month 36